Gateway West

The Gateway West project is jointly proposed by the company and Idaho Power to build and operate approximately 1,000 miles of new high-voltage transmission lines in Wyoming and Idaho. It is comprised of two major line segments:

Windstar to Populus, Segment D, will stretch approximately 488 miles starting at the Windstar substation near Glenrock, Wyoming, proceeding south to Medicine Bow and then spanning across southern Wyoming to the Populus substation near Downey, Idaho. This Segment D will include seven expanded or new substations and will enable access to existing and new generating resources, including wind, and will deliver electricity from these sources to customers.

On April 4, 2017, PacifiCorp issued its 2017 Integrated Resource Plan announcing plans to construct a portion of Segment D - Windstar to Populus. Independent of Idaho Power, PacifiCorp will initiate state and local permitting and right of way acquisition for 140 miles of 500 kV transmission line between the planned Aeolus substation near Medicine Bow, Wyoming and the Jim Bridger power plant near Point of Rocks, Wyoming.

Windstar to Populus, Segment D has been divided into three sub-segments:

  • D1 - Windstar to Aeolus: A single-circuit 230 kV line that will run approximately 75 miles between the existing Windstar substation in eastern Wyoming and the planned Aeolus substation near Medicine Bow, Wyoming.
  • D2 – Aeolus to Bridger/Anticline: A single-circuit 500 kV line running approximately 140 miles from the planned Aeolus substation to a new annex substation (Anticline) near the existing Bridger substation in western Wyoming.
  • D3 – Bridger/Anticline to Populus: A single-circuit 500 kV line running approximately 200 miles between the new annex substation (Anticline) and the recently constructed Populus substation in southeast Idaho. 

Populus to Hemingway, Segment E, originates at the Populus substation near Downey, Idaho, and includes two 500 kV single-circuit transmission lines that run approximately 502 miles across Idaho to the Hemingway substation near Melba, Idaho. The Populus to Hemingway segment will include five expanded or new substations, and will enable access to existing and new generating resources, including wind, and will deliver electricity from these sources to our customers.

Project Timeline:

  • Public Scoping – June 2008
  • Environmental Impact Statement – 2007 - 2013
  • Supplemental Environmental Impact Statement 2014 - 2016  
  • Public outreach – June 2008 through project completion
  • State and local permitting and obtaining rights of way – underway for segment D.2 Aeolus to Bridger/Anticline
    • Certificate of Public Convenience and Necessity application for segment D.2 submitted to the Wyoming Public Service Commission on June 30, 2017
  • Estimated line in service for customers – 2020 - 2024

Additional Information About the Project 

Under the National Environmental Policy Act, the Bureau of Land Management (BLM) has completed the Environmental Impact Statement (EIS) for the Gateway West project. The BLM released its final EIS on April 26, 2013, followed by the Record of Decision on November 14, 2013, providing a right-of-way grant for most of the project. The agency chose to defer its decision on the western-most portion of the project located in Idaho in order to perform additional review of the Morley Nelson Snake River Birds of Prey National Conservation Area. The BLM completed a supplemental environmental analysis for Segments 8 & 9 of the project which encompasses that area. On October 7, 2016, the BLM released its final supplemental EIS, followed by the Record of Decision on January 19, 2017. That Record of Decision was appealed to the Interior Board of Land Appeals. The Interior Board of Land Appeals remanded the January 19, 2017 Record of Decision back to Bureau of Land Management in April 2017. In May 2017, President Trump signed the Fiscal year 2017 Consolidated Appropriations Act into law which included Congressman Simpson’s agreement on Gateway West transmission line routing through the Morley Nelson Snake River Birds of Prey National Conservation Area. House Resolution 2104 (PDF) directs the Secretary of Interior to grant a right of way on the Companies’ preferred routing (Alternative 1).

Both companies will work with the Bureau of Land Management to continue through the Supplemental Environmental Impact Statement process for segment 8 (Midpoint to Hemingway) and segment 9 (Cedar Hill to Hemingway), in support of a new Record of Decision and right-of way grant for the remaining segments to comply with the House Resolution 2104. See map (PDF)

See below for additional information on public participation and project history, and visit the BLM website for more information.

Public Participation

Public input is an important part of the transmission line development process and is welcomed at all stages. In addition to public, group and individual meetings, project materials and newsletters also have been sent to more than 11,000 landowners and other interested parties throughout this process and will continue through the end of the project with continued web page and newsletter updates.

For a comprehensive list of meetings, publications and other public outreach, can be found on our Gateway West website.

To contact Rocky Mountain Power about this transmission project, please call the major construction projects message line at 801-220-4221, or email ConstructionProjects@pacificorp.com. Please be sure to include the project name – "Gateway West project" – in your inquiry.

Gateway West

Updated maps can be viewed below:

Further information also can be found at our Gateway West website