Project Overview

As part of PacifiCorp's investment in new transmission facilities announced in 2007, our company is building a new double-circuit, 345-kilovolt transmission line from the Populus Substation to be built near Downey, Idaho to the existing Ben Lomond Substation in Box Elder County, Utah, a distance of approximately 90 miles. The Ben Lomond Substation will be expanded on company-owned property to accommodate the new line. Construction is now underway on this section.

Project Timeline

  • Informational meetings – November 2007-October 2008
  • Permitting and obtaining rights of way – December 2007-April 2009
  • Construction – February 2009-December 2010
  • Estimated line in service for customers – December 2010

Additional Information About the Project

Details about this transmission section can be found in the Populus to Ben Lomond fact sheet (PDF), or get answers to frequently asked questions (PDF). Please check back periodically for updates, including the current project newsletter (PDF) and photos (image 1) that show construction activity.

Maps are available below:

Public Participation

Public input is an important part of the transmission line development process. Our company has gathered input during public open houses held in 2007 and 2008. In addition to public, group and individual meetings, project materials and newsletters (PDF) also have been sent to landowners and other interested parties.

To contact us about this project, please call 801-220-4221 or e-mail ConstructionProjects@pacificorp.com. Please be sure to include the project name - "Populus to Ben Lomond section" – in your inquiry.

(Updated January 22, 2010)

Customer Service

Customer Service

Customer service
1-888-221-7070

Report a power outage
1-877-508-5088

Report a streetlight outage