Ben Lomond to Terminal

Project Overview

The Ben Lomond to Terminal portion of the Populus-Terminal transmission line was the first segment completed as part of the Energy Gateway transmission expansion project. It added a new double-circuit, 345-kilovolt transmission line stretching approximately 46 miles from the existing Ben Lomond Substation in Box Elder County to the existing Terminal Substation located near the Salt Lake City airport. This section of the line was built alongside existing high-voltage lines and was put in service to customers in March 2010, ahead of schedule and within budget.

Project Timeline

  • Informational meetings – October 2007 - September 2008
  • Permitting and obtaining rights of way – December 2007 - October 2008
  • Construction – February 2009 - March 2010
  • In service for customers – March 2010

Additional Information About the Project

More details about this project can be found in the Ben Lomond to Terminal fact sheet (PDF) and map (PDF).

Public Participation

Public input is an important part of the transmission line development and was sought throughout the process of planning and building this project. The company gathered input during public open houses, such as those held in 2007 and 2008. In addition to public, group and individual meetings, project materials and newsletters (PDF) were sent to landowners and other interested parties.

To contact us about this project, please call 801-220-4221 or e-mail ConstructionProjects@pacificorp.com. Please be sure to include the project name – "Ben Lomond to Terminal section" – in your inquiry.
 


(Updated October 5, 2010)