The Public Utilities Policies Act of 1978 (PURPA) created an obligation for electric utilities to offer to purchase power
from, and interconnect with, qualifying generation projects. PURPA is implemented through a set of rules established by the
Federal Energy Regulatory Commission (FERC) and each state with jurisdiction over PacifiCorp. Qualifying Facilities (QFs)
must meet certain criteria as specified in the FERC rules.
Avoided cost (the cost a utility avoids as a result of the QF) forms the basis for determining QF purchase pricing. In many
states where the company operates, prices are established by a tariff applicable up to a certain-sized threshold and below.
Each state is regulated by a public service or utility commission that has certain responsibilities for the implementation
of PURPA as provided in the FERC rules. The rules and relevant orders are from each state are identified below.
Power Purchase Agreements — Standard power purchase contracts are required for some states and such contract forms are available using the links below.
For those states that do not require a standard form contract, the QF should contact PacifiCorp for the contract form used
in that state.
Interconnection — Processes are in place for interconnection at both the transmission and distribution levels. There are different contacts
for transmission and distribution information as required by FERC. Each contact can provide standard form agreements for studies,
facility construction and interconnection.
For more information:
Interconnection Requirements
The process for entering into a power purchase agreement is generally described and applicable to all QFs as shown in Schedule
38 filed in Utah, In Oregon, it is shown in Schedule 37 for projects less than 10,000 kw and Schedule 38 for project greater
than 10,000 kw.
The following links provide further information:
FERC QF self certification
California
California PUC
Idaho
Idaho PUC
Idaho - 2008 Avoided cost prices
Oregon
Oregon PUC
Oregon Schedule 37 – Avoided Cost prices and process for QFs less than 10,000 KW
Power Purchase Agreement for New QFs less than 10 MW
Power Purchase Agreement for Existing QFs less than 10 MW
Power Purchase Agreement for Off-System QFs less than 10 MW
Power Purchase Agreement for Intermittent QF Resources (i.e. Wind) less than 10,000 KW
Oregon Schedule 38 – Process for QFs greater than 10,000 KW
Non-firm Power Purchase Agreement for QFs less than 10,000 KW
Utah
Utah PUC
Utah Schedule 37 Avoided Cost Prices
Power Purchase Agreement for QFs greater than 1 MW
Utah Schedule 38 Process for QFs greater than 10,000 KW
Washington
Washington PUC Washington Schedule 37
Wyoming
Wyoming PUC Wyoming Schedule 37 Avoided Cost Prices
Qualifying facilities contact:
Manager, QF Contracts
825 NE Multnomah Street, Suite 600
Portland, OR 97232
(503) 813-5218
|